Estimated Cost of “Repairs and Re-activation of Water
Supply  Scheme Rehman Abad”, Tehsil Lachi,
District Kohat
I. Sub H No  :  Replacemeent of Rising Main 
1.      
Providing and Layig of 6” Dia GI Pipe
Qty:
600 rft OR 183 M @ Rs.2063.57 Per M  =          Rs. 377633.00
2.      
Supply / Fixing of 6” Dia Sluice Valve: 3 No.
@
Rs. 5406.20 Per No.=                                              
Rs. 16219.00
3.      
Supply/Fixing of 2” Dia Air Valve: 10 No @
       Rs. 3034.60 Per No.=                                                 
 Rs 30340.00.
4.      
Supply/Fixing of 6” Dia Non-Return Valve: 10 No:
      @
Rs. 5048.20=                                                            
Rs. 50482.00
5.       Const. of Masonry Chamber i/c
main Hole Cover: 
       3 No @Rs. 6700.00 Per No=                                        Rs. 20100.00
        Total:                                                                            Rs.
494774.00
              Add factor 3 % (+)                                                      Rs. 14843.00
             G.Total :                                                       
               Rs. 509617.00
                                                   
                            Say       
  Rs. 0.510  M
II. Sub H No. 2 : Replacement of Pipeline
1.     Providing and Laying GI Pipeline
a.    
3000 rft or 914.34 M @ Rs. 1117.65 Per M=               Rs. 1021923.00
b.    
3” Dia GI  4200 rft or 1280 M @
Rs. 765.77 Per M=   Rs. 980185.00
c.     
2” Dia GI  5100 rft or 1554 M @
Rs. 478.88 Per M =  Rs. 744180.00
d.    
1.5” Dia GI 5600 rft or 1707 M @ Rs. 387.81 Per M = Rs. 661962.00
2.    
Providing and Laying HDPE Pipe of the
following Sizes:
a.  50 mm Dia = 5200 rft or 1585 M @ Rs. 247.98
     Per M=
                                                                   Rs.393049.00
b.    
40 mm Dia = 7600 rft Or 2316 M @ Rs. 180.97 
      Per M =                                                                         Rs.
419126.00
3.     Supply/ Fixing of Following Sizes of Sluice Valves
a.       4” Dia  2 No @ Rs. 3588.13 Per No=                              Rs. 7176.00
b.      3” Dia 3 No @ Rs. 2922.63 Per No=
                             Rs 8768.00
4.     Const. of Masonry Chamber I/c Main Hole Cover 
5
No @ Rs. 6700 Per No =                                                  Rs
33500.00
Total:                                                    
                           Rs. 4359869.00
Add
factor 3 % (+)                                                              Rs. 130797.00
G.Total:                                                    
                       Rs. 4490665.00
                                                                           Say
      Rs. 4.491 M.
III. SH No
3: 
Repair of Chamber/Reservoir
1.     Provision made for Repair of Pumping Chamber/Reservoir
4 No
@ Rs. 50,000.00 per No=                                    Rs. 200,000.00
     
                                                            Say                 Rs. 0.20 M
IV. SH No. 4: Replacement of Pumping Machinery
a.    
Supply/ Installation of 80 HP Pumping Machinery capable
     to
give the required discharge= 1 set @ 
     Rs. 1000000.00 Per Set=                                           Rs.
10,00,000.00.  
b.  
Voltage Rregulator for 80 HP P/Machinery 2 No.
     @Rs.120000.00
Per No. =                                 
        Rs. 240000.00 
________________________________________________________
     Total:                                                 
Rs. 1440000.00
                                                     
Or:      Rs. 1.44 M
________________________________________________________
G.
Total( SH No 1+ 2+ 3+4) =      Rs. 6.641
M.
  Add 5 % Unforeseen Expenses  =     
Rs 0.359 M
 G.G. Total :                         Rs.07.00 Million